Manufacturer: Simple Systems
K-Lite provides experienced teams for concrete median reflector installations, with capacity for both large projects and smaller works. Method statements and risk assessments are available when required.
Teams and mobilisation
The large-project team comprises an installation manager, a foreman and three team members. This team can complete up to 900 installations per shift and can be mobilised within 48 hours. The smaller team normally consists of two or three people, completing up to 350 installations a day with mobilisation in less than 24 hours. Both teams can work concurrently, and the smaller team can be expanded within 48 hours.
Installation specifications
| Specification | Details |
|---|
| Spacing | As advised by the customer |
| Mounting height | 530 mm above the road surface. During installation, measurements are taken from the top of the guardrail for greater accuracy. |
| Fixings | Zinc-alloy security hammer-in anchors |
| Installation rate | At least one reflector per minute, up to three per minute |
| Traffic accommodation | A closed, protected lane supplied by the customer; an attenuator truck is sufficient |
Scheduling and site arrangements
Weekday daylight work is preferred. Weekend and night installations are available at no additional cost. Establishment outside Gauteng may apply, depending on quantity and distance.
Project experience
Our installation record includes GFIP packages A, B, C, D, E, F, G, H, I and L, alongside work on the N3 and at Spoornet Durban. Contractors include Group Five, WBHO, GLMB, BRCD, Siyavaya, Raubex, Power Construction, CMC, Rumdel Cape and G4.